NEW SCHEDULE OF FEES AND OTHER CHARGES
1. Bases of assessment
a. Character of occupancy or use of building/structure
b. Cost of construction
c. Floor area
d. Height
2. Regardless of the type of construction, the cost of construction of any building/structure for the purpose of assessing the corresponding fees shall be based on the following table:
Table II. G.1. On Fixed Cost of Construction per Sq. Meter
LOCATION GROUP
All Cities and Municipalities A, B, C, D, E, G, H, I F J
Php 10,000.00Php 8,000.00Php 6,000.00
3. Construction/addition/renovation/alteration of buildings/structures under Group/s and Sub-Divisions shall be assessed as follows:
a. Division A-1
Area in sq. meters Fee per sq. meter
i. Original complete construction up to 20.00 sq. meters – – – – – – – – – – – – P 2.00
ii. Additional/renovation/alteration up to 20.00 sq. meters regardless
of floor area of original construction – – – – – – – – – – – – – – – – – – – – – – – – – – 2.40
iii. Above 20.00 sq. meters to 50.00 sq. meters – – – – – – – – – – – – – – – – – – – – 3.40
iv. Above 50.00 sq. meters to 100 sq. meters – – – – – – – – – – – – – – – – – – – – – 4.80
v. Above 100 sq. meters to 150 sq. meters – – – – – – – – – – – – – – – – – – – – – – – 6.00
vi. Above 150.00 sq. meters – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 7.20
Sample Computation for Building Fee for a 75.00 sq. meters floor are:
Floor area = 75.00 sq. meters
Therefore, area bracket is 3.a. iv.
Fee = P 4.80/sq. meter
Building fee = 75.00 x 4.80 = P 360.00
b. Division A-2
Area in sq. meters Fee per sq. meter
i. Original complete construction up to 20.00 sq. meters – – – – – – – – – – – – P 3.00
ii. Additional/renovation/alteration up to 20.00 sq. meters regardless
of floor area of original construction – – – – – – – – – – – – – – – – – – – – – – – – – – 3.40
iii. Above 20.00 sq. meters to 50.00 sq. meters – – – – – – – – – – – – – – – – – – – – 5.20
iv. Above 50.00 sq. meters to 100 sq. meters – – – – – – – – – – – – – – – – – – – – – 6.60
v. Above 100 sq. meters to 150 sq. meters – – – – – – – – – – – – – – – – – – – – – – – 8.00
vi. Above 150.00 sq. meters – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 8.40
c. Division B-1/C-1/E-1, 2, 3/F-1/G-1, 2, 3, 4, 5/H-1, 2, 3, 4/I-1 and J-1, 2, 3
Area in sq. meters Fee per sq. meter
i. Up to 500 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 23.00
ii. Above 500 to 600 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 22.00
iii. Above 600 to 700 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 20.50
iv. Above 700 to 800 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 19.50
v. Above 800 to 900 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 18.00
vi. Above 900 to 1,000- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 17.00
vii. Above 1,000 to 1,500- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 16.00
viii. Above 1,500 to 2,000- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 15.00
ix. Above 2,000 to 3,000- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 14.00
x. Above 3,000 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 12.00
NOTE: Computation of the building fee for the item 3.c. is cumulative. The total area is split up into sub-areas corresponding to the area bracket indicated in the Table above. Each sub-area and the fee corresponding to its area bracket are multiplied together. The building fee is the sum of the individual products as shown in the following example:
Sample Computation for Building Fee for a building having a floor area of 3,200 sq. meters:
First 500 sq. meters @ 23.00 – – – – – – – – – – – – – – – – – – – – – – – – – P 11,500.00
Next 100 sq. meters @ 22.00 – – – – – – – – – – – – – – – – – – – – – – – – – – 2,200.00
Next 100 sq. meters @ 20.50 – – – – – – – – – – – – – – – – – – – – – – – – – – 2,050.00
Next 100 sq. meters @ 19.50 – – – – – – – – – – – – – – – – – – – – – – – – – – 1,950.00
Next 100 sq. meters @ 18.00 – – – – – – – – – – – – – – – – – – – – – – – – – – 1,800.00
Next 100 sq. meters @ 17.00 – – – – – – – – – – – – – – – – – – – – – – – – – – 1,700.00
Next 500 sq. meters @ 16.00 – – – – – – – – – – – – – – – – – – – – – – – – – – 8,000.00
Next 500 sq. meters @ 15.00 – – – – – – – – – – – – – – – – – – – – – – – – – – 7,500.00
Next 1,000 sq. meters @ 14.00 – – – – – – – – – – – – – – – – – – – – – – – – – 14,000.00
Last 200 sq. meters @ 12.00- – – – – – – – – – – – – – – – – – – – – – – – – – – 2,200.00
—————
Total Building Fee P 53,100.00
d. Division C-2/D-1, 2, 3
Area in sq. meters Fee per sq. meter
i. Up to 500 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 12.00
ii. Above 500 to 600 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 11.00
iii. Above 600 to 700 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 10.20
iv. Above 700 to 800 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 9.60
v. Above 800 to 900 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 9.00
vi. Above 900 to 1,000- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 8.40
vii. Above 1,000 to 1,500- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 7.20
viii. Above 1,500 to 2,000- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 6.60
ix. Above 2,000 to 3,000- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 6.00
x. Above 3,000 – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5.00
NOTE: Computation of the building fee in item 3.d. follows the example of Section 3.c. of this Schedule.
e. Division J-2 structures shall be assessed 50% of the rate of the principal building of which they are accessories (Section 3.a. to 3.d.).
4. Electrical Fees
The following schedule shall be used for computing electrical fees in residential, institutional, commercial and industrial structures:
a. Total Connected Load (kVA)
Fee
i. 5 kVA or less – – – – – – – – – – – – – – – – – – – – – – – – – – – P 200.00
ii. Over 5 kVA to 50 kVA – – – – – – – – – – – – – – – – – – – – – 200.00 + P 20.00/kVA
iii. Over 50 kVA to 300 kVA – – – – – – – – – – – – – – – – – – – – 1,100.00 + 10.00/kVA
iv. Over 300 kVA to 1,500 kVA – – – – – – – – – – – – – – – – – – 3,600.00 + 5.00/kVA
v. Over 1,500 kVA to 6,000 kVA – – – – – – – – – – – – – – – – -9,600.00 + 2.50/kVA
vi. Over 6,000 kVA – – – – – – – – – – – – – – – – – – – – – – – – – -20,850.00 + 1.25/kVA
NOTE: Total Connected Load as shown in the load schedule.
b. Total Transformer/Uninterrupted Power Supply (UPS)/Generator Capacity (kVA)
Fee
i. 5 kVA or less – – – – – – – – – – – – – – – – – – – – – – – – – – – P 40.00
ii. Over 5 kVA to 50 kVA – – – – – – – – – – – – – – – – – – – – – 40.00 + P 4.00/kVA
iii. Over 50 kVA to 300 kVA – – – – – – – – – – – – – – – – – – – – 220.00 + 2.00/kVA
iv. Over 300 kVA to 1,500 kVA – – – – – – – – – – – – – – – – – – 720.00 + 1.00/kVA
v. Over 1,500 kVA to 6,000 kVA – – – – – – – – – – – – – – – – -1,920.00 + 0.50/kVA
vi. Over 6,000 kVA – – – – – – – – – – – – – – – – – – – – – – – – – – 4,170.00 + 0.25/kVA
NOTE: Total Transformer/UPS/Generator Capacity shall include all transformer, UPS and generators which are owned/installed by the owner/applicant as shown in the electrical plans and specifications.
c. Pole/Attachment Location Plan Permit
i. Power Supply Pole Location – – – – – – – – – – – – – – – – – – – – – – P 30.00/pole
ii. Guying Attachment – – – – – – – – – – – – – – – – – – – – – – – – – – – – -P 30.00/attachment
This applies to designs/installations within the premises.
d. Miscellaneous Fees: Electric Meter for union separation, alteration, reconnection or relocation and issuance of Wiring Permit:
Use or Character of Occupancy Electric Meter Wiring Permit Issuance
Residential – – – – – – – – – – – – – – – – – – – – – – – – – – – -P 15.00 – – – – – – – – – P 15.00
Commercial/Industrial – – – – – – – – – – – – – – – – – – – – 60.00 – – – – – – – – – 36.00
Institutional – – – – – – – – – – – – – – – – – – – – – – – – – – – – 30.00 – – – – – – – – – 12.00
e. Formula for the Computation of Fees
The Total Electrical Fees shall be the sum of Sections 4.a. to 4.d. of this Rule.
f. Forfeiture of Fees
If the electrical work or installation is found not in conformity with the minimum safety requirements of the Philippine Electrical Codes and the Electrical Engineering Law (RA 7920), and the Owner fails to perform corrective actions within the reasonable time provided by the Building Official, the latter and/or their duly authorized representative shall forthwith cancel the permit and the fees thereon shall be forfeited.
5. Mechanical Fees
a. Refrigeration, Air Conditioning and Mechanical Ventilation:
i. Refrigeration (cold storage), per ton or fraction thereof – – – – – – – – – – – – – – – P 40.00
ii. Ice plants, per ton or fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – – 60.00
iii. Packaged/Centralized Air Conditioning Systems: Up to 100 tons, per ton. 90.00
iv. Every ton or fraction thereof above 100 tons- – – – – – – – – – – – – – – – – – – – – – 40.00
v. Window type air conditioners, per unit – – – – – – – – – – – – – – – – – – – – – – – – – – 60.00
vi. Mechanical Ventilation, per kW or fraction thereof of blower or fan, or
metric equivalent – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 40.00
vii. In a series of AC/REF systems located in one establishment, the total installed tons of refrigeration shall be used as the basis of computation for purposes of installation/inspection fees, and shall not be considered individually.
For evaluation purposes:
For Commercial/Industrial Refrigeration without Ice Making (refer to 5.a.i.):
1.10 kW per ton, for compressors up to 5 tons capacity.
1.00 kW per ton, for compressors above 5 tons up to 50 tons capacity.
0.97 kW per ton, for compressors above 50 tons capacity.
For Ice making (refer to 5.a.ii.):
3.50 kW per ton, for compressors up to 50 tons capacity.
3.25 kW per ton, for compressors above 5 up to 50 tons capacity.
3.00 kW per ton, for compressors above 50 tons capacity.
For Air conditioning (refer to 5.a.iii.):
0.90 kW per ton, for compressors 1.2 to 5 tons capacity.
0.80 kW per ton, for above 5 up to 50 tons capacity.
0.70 kW per ton, for compressors above 50 tons capacity.
b. Escalators and Moving Walks, funiculars and the like:
i. Escalator and moving walk, per kW or fraction thereof – – – – – – – – – – – – – – – P 10.00
ii. Escalator and moving walks up to 20.00 lineal meters or fraction
thereof – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 20.00
iii. Every lineal meter or fraction thereof in excess of 20.00 lineal meters – – – 10.00
iv. Funiculars, per kW or fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – 200.00
(a) Per lineal meter travel – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 20.00
v. Cable car, per kW or fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – 40.00
(a) Per lineal meter travel – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5.00
c. Elevators, per unit:
i. Motor driven dumbwaiters – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – -P 600.00
ii. Construction elevators for material – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2,000.00
iii. Passenger elevators – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5,000.00
iv. Freight elevators – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5,000.00
v. Car elevators – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5,000.00
d. Boilers, per kW:
i. Up to 7.5 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 500.00
ii. Above 7.5 kW to 22 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 700.00
iii. Above 22 kW to 37 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 900.00
iv. Above 37 kW to 52 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 1,200.00
v. Above 52 kW to 67 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 1,400.00
vi. Above 67 kW to 74 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 1,600.00
vii. Every kW or fraction thereof above 74 kW – – – – – – – – – – – – – – – – – – – – – – – – – 5.00
NOTE:
(a) Boiler rating shall be computed on the basis of 1.00 sq. meter of heating surface for one (1) boiler kW.
(b) Steam from this boiler used to propel any prime-mover is exempted from fees.
(c) Steam engines/turbines/etc. propelled from geothermal source will use the same schedule of fees above.
e. Pressurized water heaters, per unit – – – – – – – – – – – – – – – – – – – – – – – – – – – – – -P 200.00
f. Water, sump and sewerage pumps for commercial/industrial use, per kW or fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 60.00
g. Automatic fire sprinkler system, per sprinkler head – – – – – – – – – – – – – – – – – – – 4.00
h. Diesel/Gasoline ICE, Steam, Gas Turbines/Engine, Hydro, Nuclear or Solar Generating Units and the like, per kW:
i. Every kW up to 50 kW- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 25.00
ii. Above 50 kW up to 100 kW- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 20.00
iii. Every kW above 100 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 3.00
i. Compressed Air, Vacuum, Commercial, Institutional and/or Industrial Gases, per outlet – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 20.00
j. Gas meter, per unit – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 100.00
k. Power piping for gas/steam/etc., per lineal meter or fraction thereof or per cu. Meter or fraction thereof whichever is higher – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 4.00
l. Other Internal Combustion Engines, including cranes, forklifts, loaders, pumps, mixers, compressors and the like, not registered with the LTO, per kW
i. Up to 50 kW – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 10.00
ii. Above 50 kW up to 100 kW- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 12.00
iii. Every above 100 kW or fraction thereof- – – – – – – – – – – – – – – – – – – – – – – – – – – – 3.00
m. Pressure Vessels, per cu. Meter or fraction thereof – – – – – – – – – – – – – – – – – – – – P 60.00
n. Other Machinery/Equipment for commercial/Industrial/Institutional Use not elsewhere specified, per kW or fraction thereof- – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 60.00
o. Pneumatic tubes, Conveyors, Monorails for materials handling and addition to
existing supply and/or exhaust duct works and the like, per lineal meters or
fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 10.00
p. Weighing Scale Structure, per ton or fraction thereof – – – – – – – – – – – – – – – – – – – P 50.00
NOTE: Transfer of machine/equipment location within a building requires a
mechanical permit and payment fees.
6. Plumbing Fees
a. Installation Fees, one (1) “UNIT” composed of one (1) water closet,
two (2) floor drains, one (1) lavatory, one (1) sink with ordinary trap,
three (3) faucets and one (1) shower head. A partial part thereof shall
be charged as that of the cost of a whole “UNIT” – – – – – – – – – – – – – – – – – – – – – P 24.00
b. Every fixture in excess of one unit:
i. Each water closet – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 7.00
ii. Each floor drain – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 3.00
iii. Each sink – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 3.00
iv. Each lavatory – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 7.00
v. Each faucet – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.00
vi. Each shower head – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.00
c. Special Plumbing Fixtures:
i. Each slop sink – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 7.00
ii. Each urinal – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
iii. Each bath tub – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 7.00
iv. Each grease trap – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 7.00
v. Each garage trap – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 7.00
vi. Each bidet – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
vii. Each dental cuspidor – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
viii. Each gas-fired water heater – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
ix. Each drinking fountain – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.00
x. Each bar or soda fountain sink – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
xi. Each laundry sink – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
xii. Each laboratory sink – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.00
xiii. Each fixed-type sterilizer – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.00
d. Each water meter – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 2.00
i. 12 to 25 mm ø – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 8.00
ii. Above 25 mm ø – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 10.00
e. Construction of septic tank, applicable in all Groups
i. Up to 5.00 cu. Meters of digestion chamber – – – – – – – – – – – – – – – – – – – – – P 24.00
ii. Every cu. Meter or fraction thereof in excess of 5.00 cu. meters – – – – – – – – – 7.00
7. Electronics Fees
a. Central Office switching equipment, remote switching units, concentrators, PABX/
PBX’s, cordless/wireless telephone and communication systems, intercommunication system and other types of switching/routing/distribution equipment used for invoice, data image text, facsimile, internet service, cellular, paging and other types/forms of wired or wireless communications – – – – – – – – P 24.00
b. Broadcast station for radio and TV for both commercial and training purposes, CATV headed, transmitting/receiving/relay radio and broadcasting communications stations, communications centers, switching centers, control centers, operation and/or maintenance centers, call centers, cell sites, equipment silos/shelters and other similar locations/structures used for electronics and communications services, including those used for navigational aids, radar, telemetry, tests and measurements, global positioning and personnel/vehicle location – – – – – – – – – – – – – – – – P 1,000.00 per location
c. Automated teller machines, ticketing, vending and other types of electronic dispensing machines, telephone booths, pay phones, coin changers, location or direction-finding systems, navigational equipment used for land, aeronautical or maritime applications, photography and reproduction machines x-ray, scanners, ultrasound and other apparatus/equipment used for medical, biomedical, laboratory and testing purposes and other similar electronic or electronically-controlled apparatus or devices, whether located indoors or outdoors – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 10.00 per unit
d. Electronics and communications outlets used for connection and termination of voice, data, computer (including workstations, servers, routers, etc.), audio, video, or any form of electronics and communications services, irrespective of whether a user terminal is connected – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 2.40 per outlet
e. Station/terminal/control point/port/central or remote panels/outlets for security and alarm systems (including watchman system, burglar alarms, intrusion detection systems, lighting controls, monitoring and surveillance system, sensors, detectors, parking management system, barrier controls, signal lights, etc.), sound-reinforcement/background, music/paging/conference systems and the like, CATV/MATV/CCTV and off-air television, electronically-controlled conveyance systems, building automation, management systems and similar types of electronic or electronically-controlled installations whether a user terminal is connected – – – – P 2.40 per termination
f. Studios, auditoriums, theaters, and similar structures for radio and TV broadcast, recording, audio/video reproduction/ simulation and similar activities – – – – P 1,000.00 per location
g. Antenna towers/masts or other structures for installation of any electronic and/or communications transmission/reception – – – – – – – – – – – – – – – – P 1,000.00 per structure
h. Electronic or electronically-controlled indoor and outdoor signage and display systems, including TV monitors, multimedia signs, etc – – – – – – – – – – – – – – – – – – P 50.00 per unit
i. Poles and attachment:
i. Per Pole (to be paid by pole owner) – – – – – – – – – – – – – – – – – – – – – – – – – – – -P 20.00
ii. Per attachment (to be paid by any entity who attaches to the
pole of others) – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 20.00
j. Other types or electronics or electronically-controlled device, apparatus, equipment, instrument or units not specifically identified above – – – – – – – – – – – – – – P 50.00 per unit
8. Accessories of the Building/Structure Fees
a. All parts of buildings which are open on two (2) or more sides, such as balconies, terraces, lanais and the like, shall be charged 50% of the rate of the principal building of which they are a part (Section 3.a. to 3.d. of this Schedule).
b. Buildings with a height of more than 8.00 meters shall be charged an additional fee of twenty-five centavos (P 0.25) per cu. meter above 8.00 meters. The height shall be measured from the ground level up to the bottom of the roof slab or the top of girt, whichever applies.
c. Bank and Record Vaults with interior volume up to 20.00 cu. meters – – – – – – – -P 20.00
i. In excess of 20.00 cu. meters – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 8.00
d. Swimming Pools, per cu. meter or fraction thereof:
i. Group A Residential – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 3.00
ii. Commercial/Industrial GROUPS B, E, F, G – – – – – – – – – – – – – – – – – – – – – – – – 36.00
iii. Social/Recreational/Institutional GROUPS C, D, H, I – – – – – – – – – – – – – – – – – 24.00
iv. Swimming pools improvised from local indigenous materials such as rocks, stones and/or small boulders and with plain cement flooring shall be charged 50% of the above rates.
v. Swimming pool shower rooms/locker rooms:
(a) Residential GROUP A – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 6.00
(b) Group B, E, F, G – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 18.00
(c) Group C, D, H – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – -12.00
e. Construction of firewalls separate from the building:
i. Per sq. meter or fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 3.00
ii. Provided, that the minimum fee shall be – – – – – – – – – – – – – – – – – – – – – – – – – – 48.00
f. Construction/erection of towers: Including Radio and TV towers, water tanks supporting structures and the like:
Use or Character of Occupancy Self- Supporting Trilon (Guyed)
i. Single detached dwelling units – – – – – – – – – – – – -P 500.00 – – – – – – – – – – – – P 150.00
ii. Commercial/Industrial (Groups B, E, F, G) up to
10.00 meters in height – – – – – – – – – – – – – – – – – – 2,400.00 – – – – – – – – – – – – – 240.00
(a) Every meter or fraction thereof in excess of
10.00 meters – – – – – – – – – – – – – – – – – – – – – – – 120.00 – – – – – – – – – – – – – 12.00
iii. Educational/Recreational/Institutional (Groups C, D, H, I)
up to 10.00 meters in height – – – – – – – – – – – – – 1,800.00 – – – – – – – – – – – – – 120.00
(a) Every meter or fraction thereof in excess of
10.00 meters – – – – – – – – – – – – – – – – – – – – – – – 120.00 – – – – – – – – – – – – – 12.00
g. Storage Silos, up to 10.00 meters in height – – – – – – – – – – – – – – – – – – – – – – – – P 2,400.00
i. Every meter or fraction thereof in excess of 10.00 meters – – – – – – – – – – – – 150.00
ii. Silos with platforms or floors shall be charged an additional fee in accordance with Section 3.e. of this Schedule.
h. Construction of Smokestacks and Chimneys for Commercial/Industrial Use Groups B, E, F and G:
i. Smokestacks, up to 10.00 meters in height, measured from the base – – – P 240.00
(a) Every meter or fraction thereof in excess of 10.00 meters – – – – – – – – – – – 12.00
ii. Chimney up to 10.00 meters in height, measured from the base – – – – – – – – – 48.00
(a) Every meter or fraction thereof in excess of 10.00 meters – – – – – – – – – – – – 2.00
i. Construction of Commercial/Industrial Fixed Ovens, per sq. meters or fraction thereof of interior floor areas – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 48.00
j. Construction of Industrial Kiln/Furnace, per cu. Meter or fraction thereof of
volume – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.00
k. Construction of reinforced concrete or steel tanks or above ground Groups A and B, up to 2.00 cu. meters – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – -12.00
i. Every cu. m or fraction thereof in excess of 2.00 cu. meters – – – – – – – – – – – P 12.00
ii. For all other than Groups A and B up to 10.00 cu. meters – – – – – – – – – – – – – 480.00
(a) Every cu. meter or fraction thereof in excess of 10.00 cu. meters – – – – – 24.00
l. Construction of Water and Waste Water Treatment Tanks: (Including Cisterns, Sedimentation and Chemical Treatment Tanks) per cu. meter of volume – – – – P 7.00
m. Construction of reinforced concrete or steel tanks except for Commercial/ Industrial Use:
i. Above ground, up to 10.00 cu. meters – – – – – – – – – – – – – – – – – – – – – – – – – – P 480.00
Every cu. m or fraction thereof in excess of 10.00 cu. meters – – – – – – – – – – 480.00
ii. Underground, up to 20.00 cu. meters – – – – – – – – – – – – – – – – – – – – – – – – – – – 540.00
Every cu. meter or fraction thereof in excess of 20.00 cu. meters – – – – – – – – 24.00
n. Pull-outs and Reinstallation of Commercial/Industrial Steel Tanks:
i. Underground, per cu. meter or fraction thereof of excavation – – – – – – – – – – P 3.00
ii. Saddle or trestle mounted horizontal tanks, per cu. meter or fraction thereof of volume tank – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 3.00
iii. Reinstallation of vertical storage tanks shall be the same as new construction fees in accordance with Section 8.k. above.
o. Booths, Kiosks, Platforms, Stages and the like, per sq. meter or fraction thereof of floor area:
i. Construction of permanent type – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 10.00
ii. Construction of temporary type – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5.00
iii. Inspection of knock-down temporary type, per unit – – – – – – – – – – – – – – – – – – – 24.00
p. Construction of buildings and other accessory structures within cemeteries and memorial parks:
i. Tombs, per sq. meter of covered ground areas – – – – – – – – – – – – – – – – – – – – P 5.00
ii. Semi-enclosed mausoleums whether canopied or not, per sq. meter of built-up area – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 5.00
iii. Totally enclosed mausoleums, per sq. meter of floor area – – – – – – – – – – – – – – 12.00
iv. Multi-level interment niches, per sq. meter, per level – – – – – – – – – – – – – – – – – – 5.00
v. Columbarium, per sq. meter – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 18.00
9. Accessory Fees
a. Establishment of Line and Grade, all sides fronting or abutting streets, esteros, rivers and creeks, first 10.00 meters – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 24.00
i. Every meter or fraction thereof in excess of 10.00 meters – – – – – – – – – – – – – – – 2.40
b. Ground Preparation and Excavation Fee
i. While the application for Building Permit is still being processed, the Building Official may issue Ground Preparation and Excavation Permit (GP&EP) for foundation, subject to the verification, inspection and review by the Line and Grade Section of the Inspection and Enforcement Division to determine compliance to line and grade, setbacks, yards/easements and parking requirements.
(a) Inspection and Verification Fee – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 200.00
(b) Per cu. meters of excavation – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 3.00
(c) Issuance of GP & EP, valid only for thirty (30) days or superseded upon issuance of Building Permit – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 50.00
(d) Per cu. meter of excavation for foundation with basement – – – – – – – – – – – 4.00
(e) Excavation other than foundation or basement, per cu. meter – – – – – – – – -3.00
(f) Encroachment of footings or foundations of buildings/structures to public areas as permitted, per sq. meter or fraction thereof of footing or foundation encroachment – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 250.00
c. Fencing Fees:
i. Made of masonry, metal, concrete up to 1.80 meters in height, per lineal meter or fraction thereof – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 3.00
ii. In excess of 1.80 meters in height, per lineal meter of fraction thereof – – – – – – 4.00
iii. Made of indigenous materials, barbed, chicken or hog wires, per lineal
meter – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 2.40
d. Construction of Pavements, up to 20.00 sq. meters – – – – – – – – – – – – – – – – – – – P 24.00
e. In excess of 20.00 sq. meters or fraction thereof of paved areas intended
for commercial/industrial/institutional use, such as parking and sidewalk
areas, gasoline station premises, skating rinks, pelota courts, tennis and
basketball courts and the like – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 3.00
f. Use of Streets and Sidewalks, Enclosures and Occupancy of Sidewalks up to
20.00 sq. meters, per calendar month – – – – – – – – – – – – – – – – – – – – – – – – – – – – -P 240.00
i. Every sq. meter or fraction thereof in excess of 20.00 sq. meters – – – – – – – P 12.00
g. Erection of Scaffolding Occupying Public Areas, per calendar month.
i. Up to 10.00 meters in length – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 150.00
ii. Every lineal meter or fraction thereof in excess of 10.00 meters – – – – – – – – – – 12.00
h. Sign fees:
i. Erection and anchorage of display surface, up to 4.00 sq. meters of signboard area – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – P 120.00
(a) Every sq. meter or fraction thereof in excess of 4.00 sq. meters – – – – – – – 24.00
ii. Installation Fees, per sq. meter or fraction thereof of display surface:
Type of Sign Display Business Signs Advertising Signs
Neon P 36.00 P 52.00
Illuminated 24.00 36.00
Others 15.00 24.00
Painted-on 9.60 18.00
iii. Annual Renewal Fees, per sq. meter of display surface or fraction thereof:
Type of Sign Display Business Signs Advertising Signs
Neon P 36.00, min fee shall be P 124.00 P 46.00, min fee shall be P 200.00
Illuminated P 18.00, min fee shall be P 72.00 P 38.00, min fee shall be P 150.00
Others P 12.00, min fee shall be P 40.00 P 20.00, min fee shall be P 110.00
Painted-on P 8.00, min fee shall be P 30.00 P 12.00, min fee shall be P 100.00
i. Repairs Fees:
i. Alteration/renovation/improvement on vertical dimensions of building/structures in square meter, such as facades, exterior and interior walls, shall be assessed in accordance with the following rate, For all Groups – – – – – – – – – – – – – – – – – – P 5.00
ii. Alteration/renovation/improvement on horizontal dimensions of buildings/structures, such as floorings, ceilings and roofing shall be assessed in accordance with the following rate, For all Groups – – – – – – – – – – – – – – – – – – – 5.00
iii. Repairs on buildings/structures in all Groups costing more than five thousand pesos (P 5,000.00) shall be charged 1% of the detailed repair cost (itemized original materials to be replaced with same or new substitute and labor)
j. Raising of Buildings/Structures Fees:
i. Assessment of fees for raising of any buildings/structures shall be based on the new usable area generated.
ii. The fees to be charged shall be as prescribed under Sections 3.a. to 3.e. of this Schedule, whichever Group applies.
k. Demolition/Moving of Buildings/Structures Fees, per sq. meter of area or dimensions involved:
i. Buildings, in all Groups per sq. meter floor area – – – – – – – – – – – – – – – – – – – – P 3.00
ii. Building Systems/Frames or portion thereof per vertical or horizontal dimensions, including Fences – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – 4.00
iii. Structures of up to 10.00 meters in height – – – – – – – – – – – – – – – – – – – – – – – – – 800.00
(a) Every meter or portion thereof in excess of 10.00 meters – – – – – – – – – – – – 50.00
iv. Appendage of up to 3.00 cu. meter/unit – – – – – – – – – – – – – – – – – – – – – – – – – – – 50.00
(a) Every cu. meter or portion thereof in excess of 3.00 cu. meters – – – – – – – 50.00
v. Moving Fee, per sq. meter of area of building/structure to be moved – – – – – – – 3.0